Home News 2011 Prominvestbank Data Center for 92 days
Prominvestbank Data Center for 92 days
04/04/2011
SOLID Construction Company successfully finished the construction of Data Center engineering infrastructure for Prominvestbank. In this project SOLID was involved as subcontractor of Incom company.

The Data Center was built to provide a platform for creating new client services that will allow the bank to strengthen its market positions. SOLID carried out the complex of construction and assembling works for flexible installation of engineering infrastructure systems.

The works included engineering systems arrangement and finishing as follows:
  • Disassembling of interior finishing, wood and metal constructions.
  • Finishing: floors, walls, ceilings.
  • Engineering systems: water supply system, sewage, HVAC.
The project was completed in record short terms. The process from project design to its putting into operation took 92 calendar days. As a result the client received completed project that entirely corresponded to technical assignment in specified terms.